FRIENDS OF KENNEBEC SALMON STOPS FISH KILL
AT COBBOSSEECONTEE STREAM,
GARDINER, MAINE -- OCTOBER 2002



Adult American eels chopped to pieces by the turbines of the American Tissue Dam, Cobbosseecontee Stream, Gardiner, Maine. Evening of 8 October 2002. The dam is operated by CHI Energy, Andover, Massachusetts.



ENFORCEMENT ORDER BY MAINE DEPARTMENT OF ENVIRONMENTAL PROTECTION



October 10, 2002

Certified Nos. 7000 1670 0008 7878 4162
7000 1670 0008 7878 4155

Skip Medford
CHI Operations, Inc.
Andover Business Park
200 Bulfinch Drive
Andover, MA 01810

Thomas R. Brown
Ridgewood Maine Hydro Partners, L.P.
947 Linwood Ave.
Ridgewood, N.J. 07450

Also sent via fax to CHI on October 10, 2002 (978-681-7727)

Re: American Tissue Dam-FERC No. 2809-ME


Dear Messrs. Medford and Brown:

I want to begin by thanking you for your prompt response to our requests for corrective action at this facility. As of the time this letter is written, CHI has installed a plunge pool box for alewives and opened one of the deep gates some six inches. It is my understanding that CHI has verbally agreed to shut down the turbine, effective today, from dusk till dawn every day until November 15, 2002. It is also my understanding that today CHI installed two metal plates, each several feet high, at the base of the trash screens that will physically block eels from swimming along the bottom and into the influent to the turbines. Because eels typically travel along the bottom, hopefully this will prove to be an effective deterrent.

Although these corrective actions are very positive steps in the right direction, we need to assure that the facility is brought into compliance with Maine law and continues in compliance. Therefore, the Department continues to request that CHI Operations, Inc. and/or Ridgewood take any and all necessary measures, subject to DEP and/or DMR approval, to prevent fish mortality due to downstream migration at the American Tissue Dam (FERC No. 2809) in Gardiner, Maine. Such measures may include, but may not be limited to, temporarily shutting down the turbine and if necessary, draining the head pond until the downstream migration of eels and alewives is done for this year.


It is the Department's position that you are in violation of Title 38 M.R.S.A. § 464 for rendering the receiving waters unsuitable "as habitat for fish and other aquatic life." Our position is supported by an ongoing fish kill and evidence of other significant fish kills that occurred at the facility over the past several years.

This Department's request for corrective action was initially conveyed to you via a voicemail message shortly after 5:00 P.M. on October 7. On October 8, 2002, CHI responded by increasing the opening of the deep gate nearest to the generating station intake to approximately 5 inches. Increasing the gate opening revealed that the previous opening of some three inches (opened on September 15, 2002) was partially blocked by debris. As soon as the gate was opened to 5 inches, there was a moderate increase in water through the gate. Several minutes after the gate opening was increased to 5 inches, a plume of muddy water exited through the gate and the flow increased considerably. I later learned from John Bogert that CHI staff place sandbags in front of the gates each fall to minimize leakage. Apparently, during the period September 15-October 8, 2002, although the gate was opened some three inches, the effective width of the opening was less than that.

During my site visit on October 8, I requested of Mr. Bogert that CHI place a screen below the powerhouse discharge to determine if eels continue to be killed in the turbines in spite of the increased flow through the deep gate. He refused because, as he stated, the screen would become clogged.

On October 9, CHI closed the deep gate and opened the gate furthest from the powerhouse intake to approximately six inches. It is my understanding the possibility of shutting down the turbines during the night time hours was discussed between CHI and John Perry of the Dept. of Marine Resources at this time. On this date, CHI built a structure on the dam apron to act as a plunge pool for downstream migrating alewives. After the structure was built, a small school of alewives was seen going over the dam, entering and exiting the structure, and entering the stream. During my visit to the site this afternoon, I observed that the flow to the plunge pool box had been cut off and workmen were busy repairing the box because one side wall had bowed out from the water pressure. I observed two dead alewives inside the box. Once the box was braced and the flashboard was removed, I observed that the box has considerable leakage. The integrity of the box should be closely monitored and if leakage becomes excessive, it should be repaired or replaced.

On October 8, 9, and 10, dead eels were observed and collected below the outfall of the power generation station. On October 9 alone, evidence of more than one hundred dead eels was collected and removed from the stream. Today, in excess of forty dead and dying eels were found in the stream below the power generation facility. These were still found in spite of increased stream flows that may have washed additional eels and eel parts downstream.

It is this Department's position that the corrective measures taken by CHI prior to today have not been effective with regard to the killing of eels. Conversely, there is evidence, in the form of dead and dying eels, that the corrective measures have been ineffective. Therefore, effective immediately, the Department of Environmental Protection requests that, at a minimum, you take the following corrective actions:

Cease all power production by shutting down the turbine every day from dusk to dawn beginning today, October 10, 2002 until November 15, 2002 (as noted above, it is my understanding that CHI has verbally committed to do this);

Maintain continuous downstream eel passage by keeping one or more deep gates open a minimum of six inches until November 15, 2002;

3) Due to concerns that flows into the headpond through the CHI operated New Mills dam may be cut back at night, please ensure that sufficient flow is maintained to maximize the downstream passage of eels through the deep gate during non-generating hours until November 15, 2002;

Maintain an effective downstream alewife fish passage device until November 15, 2002;

Visit the facility a minimum of once daily to monitor the effectiveness of downstream fish passage; and,

To determine the efficacy of these corrective measures, install a screen or other device below the outfall of the power plant, subject to approval by the Dept. of Marine Resources, and report any numbers of dead and dying eels collected to the DEP daily. This screening device is to remain in place until November 15, 2002 unless approval to remove it sooner is granted by the DEP.

It is likely that this Department will issue a formal Notice of Violation in this matter.

Due to the repeated nature of these violations, the Department may propose an Administrative Consent Agreement and Enforcement Order. The Department's actions in this regard will be guided in part by your willingness to permanently correct the problems at the facility.

Thank you again for your very prompt response and for your anticipated continued cooperation in this matter. Please contact me within five (5) days of receipt of this letter with your response to these requests. If you have any comments or questions, please call me at (207) 287-7783. Please be advised that the State is on shutdown tomorrow and October 14. I will, however, visit the office during each of the next four days to check my voicemail and email messages.

Sincerely,



John M. Glowa, Sr.
Enforcement Section
Division of Water Resource Regulation
Bureau of Land & Water Quality

Cc: Tom Squires-DMR
Gail Wipplehauser-DMR
John Perry-DMR
Dana Murch-DEP
Carol Blasi-Dept. of Attorney General


MORE INFORMATION ...